On June 18, 2021, the Ministry of Transport issued a decision approving the contractor selection results for package XL04: Construction of the section Km419+600 – Km430+ 000 (including survey, construction drawing design), North – South expressway component project Nghi Son – Dien Chau section.

The North – South Expressway Component Project, the Nghi Son – Dien Chau section is 50km long, passing through the two provinces of Thanh Hoa and Nghe An (Artwork)

The Ministry of Transport issued a decision approving the results of contractor selection for package XL04: Construction of the section Km419+600 – Km430+ 000 (including survey, construction drawing design), North Expressway component project – South of Nghi Son – Dien Chau section.

According to the approval decision of the Ministry of Transport, the winning contractor is a joint venture between CIENCO4 Group Joint Stock Company – Tan Nam Construction Joint Stock Company – Truong Son Construction Investment Joint Stock Company.

The winning value of the package is VND 1,139.53 billion (including provisions and 10% VAT). Type of contract according to the combined unit price (survey part: According to the fixed unit price; Construction drawing design: Package; Construction and installation: according to the adjusted unit price).

This bidding package uses state budget capital, the contract period is 24 months. This is the 2nd bidding package in 4 construction and installation packages under the North – South expressway component project of Nghi Son – Dien Chau section to complete contractor selection.

Previously, on June 11, the Ministry of Transport issued a decision approving the contractor selection results for package XL01 of Nghi Son – Dien Chau expressway project. The winning contractor is a joint venture of Son Hai Group Company Limited – Deo Ca Group Joint Stock Company – Deo Ca Construction Joint Stock Company. The winning value of package XL01 is more than 1,158 billion VND (including provision and 10% VAT).

It is known that the North – South expressway component project, the Nghi Son – Dien Chau section is 50km long, passing through the two provinces of Thanh Hoa and Nghe An. In the completion phase, the project will build a scale of 6 lanes, road bed 32.25m, design speed 100 – 120km/h.

In the immediate future, in the phase of divergence, the project will build 4 lanes, 17m road bed, design speed 80km/h. The project has a total investment of about VND 7,293 billion, using state budget capital, the project construction period is about 2 years.

(Source: Baogiathong.vn)